|
|
PIPELINE AND FACILITIES OPERATIONS
MANUAL
OVERVIEW
|
Note to Clients:
The Oil and Gas Commission (OGC) has modified the system introduced last year
for managing pipelines. This system and related regulatory practices,
application forms and processes are described in a new manual. Operators are
directed to refer to this new manual for all aspects of pipeline activity.
The table at the end of this document summarizes the changes that have been
made to the pipeline regulatory process. The following information provides a
more detailed explanation of the same changes and some of the rationale for
these changes.
The Oil and Gas Commission continues to phase in a "performance-based" approach
to managing oil and gas industry performance in British Columbia. OGC effort
will shift from reviewing preliminary surface and technical information at the
front end of the planning process to assessing the performance of companies'
activities against clear, relevant standards.
Starting with the 2004/2005 season, the OGC implemented a number of significant
changes that are designed to improve the efficiency and effectiveness of
pipeline planning and construction in the industry, as well as application
review and pipeline activity compliance monitoring:
-
The PL 101 form is no longer part of the OGC review process. Engineering
companies will therefore no longer receive separate letters from the OGC
indicating Certificate and Project Numbers. Engineered technical drawings and
detailed specifications are not required at the surface application stage. This
information will be submitted at the notice to construct stage after the
surface authorizations have been issued and companies are undertaking
construction;
-
Requirements for surface activities and technical specifications will be
reflected in regulatory standards until best management practices can be
developed. The best management practices will include forestry, aquatic and
terrestrial ecosystems, stakeholder and public consultation, and archaeology,
and
-
Pipeline surface access applications will be treated as routine or non-routine.
Applications will be treated as routine where either:
-
the pipeline is included in a General Development Plan (GDP) which either has
approval in principle or is being processed by the OGC, and the length and
location of the pipeline are the same as what was proposed in the GDP; or
-
the application meets the following requirements:
-
the company commits to following all regulatory standards and best management
practices;
-
Conflicts with landowners, tenure holders and stakeholders have been resolved;
and
-
The pipeline is located outside of CSA class 2, 3 or 4 locations;
-
The pipeline is located outside the Muskwa-Kechika Management area, Major River
Corridors, and Special and Protected Management Land Use Areas as defined in
the LRMPs;
-
The pipeline project is within northeastern BC.
For routine applications, the OGC's role will be limited to the following:
-
Completion of First Nations consultations (where the OGC has determined that
consultation is required).
-
Completion of status checks for private and Crown land. This will identify
potential surface ownership and tenure conflicts. Note: companies will likely
be able to complete this step starting in late 2005 with the implementation of
the Integrated Land and Resource Registry (ILRR); and
-
Issuance of surface authorizations including:
-
Land Act - temporary permit to occupy Crown land;
-
Forest Act - cutting permit; and
-
Water Act (if applicable) - permission for changes in or about a stream.
Temporary rights to occupy have been lengthened from 6 months to 24 months. The
OGC will continue to issue the documentation for the three-year License of
Occupation which is now issued at the final segment of notification of Leave to
Open or at the conclusion of the 2 year right of occupancy, or at the
conclusion of the 2 year right of occupancy, whichever comes first.
Pipeline surface access authorizations under the Water Act, Land Act and Forest
Act will be issued regardless of the status of wells (provided the well has
been approved). Companies are no longer required to provide a Notice of Proven
Well to the OGC. This component is now within the notice of Leave to Construct.
Companies are able to make minor routing changes or carry out work within a 150
metre corridor containing the proposed right of way for those lines crossing
new land and where no other linear disturbance exists. Changes in the routing
and right of way within the corridor will be filed with the OGC upon filing the
as-cleared surface construction plans which must be submitted with the
notification of Leave to Open. The formal Statutory Right of Way is issued when
the final legal survey (Statutory Right of Way Plan) is submitted (within two
years of Certificate of Operations being issued).
As well, companies can identify temporary work spaces within the 150 metre
corridor.. These temporary work spaces must be identified in the application on
the construction plan, or if utilizing a corridor, only the total area required
for the workspaces must be shown on the construction plan. Companies pay
stumpage and consideration on this additional area cleared for temporary work
space.
Companies are able to obtain approval of up to five segments of a pipeline
project. Initially, this will be achieved by grouping less complex segments
that meet "routine" criteria under one application. More complex and sensitive
segments should be submitted under a separate non-routine application. The
maximum number of segments allowed per application will be reviewed and may be
revised for the 2006/2007 season.
Start
Original Process |
Phase 1
Previous Season |
Phase 2
Current Changes |
-
PL101/103 submitted, along with a cover letter on first submission
-
PL101/103 requires detailed pipe/facility specs
-
LTO is requested after pressure tests are preformed by way of a letter
-
PL102/PL104 submitted after construction
-
PL102/PL104 also requires detailed pipe specs (often different from PL101
specs)
-
Certificate of Operations granted.
-
Notification of cancellation, abandonment (prior to 1997), etc. done via a
letter of notification
-
Modifications, repairs, relocations, etc. done through the PL101 / PL102 system
|
-
Total overhaul of the pipeline application process
-
Removal of the PL101 / PL102 system
-
Change to a new set of forms, which separates and identifies different pipeline
activities
-
Surface Rights Form identifies routine vs. non-routine based on geographic
areas, special management areas, and following BMPS as well as within existing
ROW or GDP
-
Notice of Intent Form - notifies OGC of activities taking place on existing
projects
-
Notice of Construction Start Form - self explanatory
-
Notice of Pressure Test Form - self explanatory
-
Leave to Open - at this stage all pipeline specifications are required
-
As-built Form - drawings required at this point, final notice of construction
finish
|
-
Purpose of these changes is to further "lean out" the requirements and clarify
the process, while maintaining legislative requirements
-
Process for amendments and revisions on the Surface Rights Application Form
have been included
-
P.Eng sign off required only on the Leave to Open and As-Built forms
-
Regulatory Standards (Legal BMPs) have been outlined
-
PL103/104 removed and incorporated into the new system
-
Minor requirement changes on some of the forms
-
Forms have been further simplified with clearer directives
-
Most technical specifications are now required at the As-Built stage rather
than the Leave to Open
-
Major River Corridors and Special and Protected Management Land Use categories
as defined in the LRMPs are now non-routine triggers
|
|
|
|